Timeline
While development and changes are planned at each of California Pacific Medical Center's campuses, the cornerstone of the plans is the new acute care and Women & Children's hospital at Cathedral Hill.
The following is an overview of the anticipated environmental review process and construction schedule.
Review Process
Environmental Review
Environmental Impact Report: Ongoing
2009 EIR Public Scoping Session: Tuesday, June 9, 2009
See the Events page for more information.
The San Francisco Planning Department will mail a notification letter approximately 2 weeks prior to the EIR scoping session informing interested residents about the date and time of the session. Please contact the SF Planning Department if you would like to be notified.
Approvals: Barring any delays, as soon as April-May 2010
Construction
Cathedral Hill Campus
New Hospital Construction: 2010 - 2014
New Medical Office Building Construction: 2010 - 2014
St. Luke's Campus
New Hospital Construction: 2010 - 2012
Future Expansion: 2018 - 2020*
Pacific Campus
Move Acute Care services to Cathedral Hill Campus: 2014
Renovate Hospital to Ambulatory Care Center: 2015 - 2016*
New Webster/Sacramento St. Underground Garage: 2016 - 2018*
New ACC Addition: 2018 - 2019*
Davies Campus
New Neuroscience Institute: 2010 - 2012
New Castro/14th St. Medical Office Building: 2018 - 2020*
New Castro/14th St. Underground Garage: 2018 - 2020*
California Campus
No Construction planned at this time
Move Acute Care services to Cathedral Hill Campus: 2014
Move Ambulatory services to Pacific Campus: 2016 - 2019
* Please note that plans marked with an asterisk are long-term projects. Project approvals are not being sought for long-term projects at this time.